Uh_huh_him
Well-known member
- Sep 28, 2011
- 13,375
Hi NSC
I'm after some advice having just had a protracted issue with getting some flooring laid in our kitchen-diner.
I know there are a few flooring experts on here so hopefully you can come up with something helpful..
We decided to refresh the flooring in our house.
Having had a couple of local companies come to measure up and never come back to us with a price.
I went to Carpetright to see if they could help us.
We selected various flooring for the house and booked an estimation,
The estimator was here for an hour or so doing a pretty thorough job.
We have an area of the kitchen which has ceramic tiles on the floor and the rest of the floor is laminate.
He explained that the LVT we had chosen, would have to be laid on top of the ceramic tiles and the remaining area built up to meet the same level.
Any slight discrepancy in height would be covered by a separator bar between the two areas.
We are also having LVT in the lounge so the areas would probably have to be brought up in both rooms.
Not ideal, but agreed to it and when the estimate came through, negotiated a bit on price and eventually signed the finance agreement.
The fitting date was booked and I duly disconnected all the appliances and cleared the rooms so the fitters would have a good run at the job.
On the day the fitter turned up and informed me that he would be unable to meet the requirements of the job, as the amount of building up for the is too much.
Several other issues with the plan he had been given meant that he was unable to proceed, but what was required is "a builder's job".
Much to-ing an fro-ing with Carpetright then occurred.
In the end, I explained that I'm happy for them to re-estimate the job, but wanted a decent job and not some lash up.
A few day's later Carpetright's fitters say they are unable to do the job and not being offered any alternative, I have requested they cancel the order.
Pretty irritating.
Now for the advice bit...
I need to look elsewhere to get this done.
If I'm getting builders in, i would rather they took the tiles up as well and levelled the whole floor off and laid the LVT, at one level throughout kitchen/diner/lounge.
Is this a foolhardy approach?
If not, how much extra effort/cost are we talking about?
Are there any better approaches?
Thanks in advance for any advice you can offer.
I'm after some advice having just had a protracted issue with getting some flooring laid in our kitchen-diner.
I know there are a few flooring experts on here so hopefully you can come up with something helpful..
We decided to refresh the flooring in our house.
Having had a couple of local companies come to measure up and never come back to us with a price.
I went to Carpetright to see if they could help us.
We selected various flooring for the house and booked an estimation,
The estimator was here for an hour or so doing a pretty thorough job.
We have an area of the kitchen which has ceramic tiles on the floor and the rest of the floor is laminate.
He explained that the LVT we had chosen, would have to be laid on top of the ceramic tiles and the remaining area built up to meet the same level.
Any slight discrepancy in height would be covered by a separator bar between the two areas.
We are also having LVT in the lounge so the areas would probably have to be brought up in both rooms.
Not ideal, but agreed to it and when the estimate came through, negotiated a bit on price and eventually signed the finance agreement.
The fitting date was booked and I duly disconnected all the appliances and cleared the rooms so the fitters would have a good run at the job.
On the day the fitter turned up and informed me that he would be unable to meet the requirements of the job, as the amount of building up for the is too much.
Several other issues with the plan he had been given meant that he was unable to proceed, but what was required is "a builder's job".
Much to-ing an fro-ing with Carpetright then occurred.
In the end, I explained that I'm happy for them to re-estimate the job, but wanted a decent job and not some lash up.
A few day's later Carpetright's fitters say they are unable to do the job and not being offered any alternative, I have requested they cancel the order.
Pretty irritating.
Now for the advice bit...
I need to look elsewhere to get this done.
If I'm getting builders in, i would rather they took the tiles up as well and levelled the whole floor off and laid the LVT, at one level throughout kitchen/diner/lounge.
Is this a foolhardy approach?
If not, how much extra effort/cost are we talking about?
Are there any better approaches?
Thanks in advance for any advice you can offer.