A small update from yesterday (with camera)

Work continuing on the banking. In the last photo, the guys are dislodging all the loose stuff to get ready for the concrete blasting.
 

Attachments

  • 030311 3.jpg
    030311 3.jpg
    763.4 KB · Views: 551
  • 030311 1.jpg
    030311 1.jpg
    859.1 KB · Views: 549
  • 030311 4.jpg
    030311 4.jpg
    898 KB · Views: 549
  • 030311 2.jpg
    030311 2.jpg
    763.9 KB · Views: 552
Last edited:




deletebeepbeepbeep

Well-known member
May 12, 2009
21,657
Are they "cladding"? the entire slope, or leaving the majority as open chalk?

It's existing that they're beginning to clear up the periphery areas.
 


Everest

Me
Jul 5, 2003
20,741
Southwick
The slope will be blasted with concrete, DBBB.
A bit dangerous to leave it as open chalk.
 




Everest

Me
Jul 5, 2003
20,741
Southwick
I presume those bits were done yesterday. There was a cement mixer there at the time but no blasting was actually going on.
There is a reinforced mesh lining the bottom section which gives extra strength and something for the concrete to bind on to.
 






Everest

Me
Jul 5, 2003
20,741
Southwick
Trenches were dug, and blue and black pipes laid a few months ago.
Whether those were for drainage or not I'm not sure, but I would have thought so.
 